ANALYSIS OF PREVENTIVE MAINTENANCE 110 VDC SYSTEM AT PLTM GUNUNG WUGUL PT. PLN INDONESIA POWER MRICA PGU
DOI:
https://doi.org/10.58436/jeepa.v3i2.1742Keywords:
Electricity, Battery 110 VDC, Preventive maintenanceAbstract
The battery is a back-up for the DC electrical system which is closely related to the protection system in a generator, so to find out the routine maintenance system of the 110 VDC battery system used at the Mount Wugul PLTM. This maintenance will measure the voltage and quality of the battery water in the battery. The aim of the research is to test the 110 VDC battery for daily maintenance, a visual inspection is carried out to ensure the physical condition of the battery is in good condition, to ensure the 110V DC battery remains in a stable condition and is ready to supply DC power to auxiliary equipment when an emergency occurs. From the test results, it was found that the voltage drop in cells number 1 and 7 was recorded at 0.3661 VDC and 1.1948 VDC respectively. It was necessary to take corrective action or replace the battery cells. By measuring the specific gravity of each battery cell, the average value of the specific gravity of the battery was 1,214.59, which is included in the recharge category, meaning that the battery needs to be re-charged. So the results of measuring these two voltages show that the respective voltage balance between positive to ground and negative to ground is in accordance with standards
References
I. Pamungkas, H. T. Irawan, and T. M. A. Pandria, “Implementasi Preventive Maintenance Untuk Meningkatkan Keandalan Pada Komponen Kritis Boiler Di Pembangkit Listrik Tenaga Uap,” VOCATECH: Vocational Education and Technology Journal, vol. 2, no. 2, pp. 73–78, 2021, doi: 10.38038/vocatech.v2i2.53.
N. Cholis and R. N. Prasetyono, “ANALYSIS OF THE EFFECT OF MAGNETIC LOCATION AND ADDITION OF BERRIER FLUX ON BACK EMF VALUE ON PMSG 12S8P USING FEM METHOD,” Journal of Electronic and Electrical Power Application (JEEPA), vol. 2, no. 1, pp. 65–71, 2022, doi: https://doi.org/10.58436/jeepa.v2i1.1040.
H. E. Mantiri, M. Rumbayan, and G. M. C. Mangindaan, “Perencanaan Pembangkit Listrik Tenaga Listrik Minihidro Sungai Moayat Desa Kobo Kecil Kota Kotamobagu,” Jurnal Teknik Elektro dan Komputer, vol. 7, no. 3, pp. 227–238, 2018.
E. Debit, T. Kebutuhan, P. Listrik, T. Minihidro, S. Cisanggiri, and K. Cihurip, “s IKLU s,” vol. 9, no. 1, pp. 82–94, 2023.
R. Mubarok, R. N. Prasetyono, and Z. Alfarikhi, “Analisis Sistem Grounding Menggunakan Elektroda Ground Rod Jenis Tembaga Pada Gedung A dan D di Universitas Peradaban,” Journal of Telecommunication, Electronics, and Control Engineering (JTECE), vol. 4, no. 2, 2022, doi: 10.20895/jtece.v4i2.708.
W. Wijaya, J. Windarto, and K. Karnoto, “Analisa Perencanaan Pembangkit Listrik Tenaga Mini Hidro Di Sungai Logawa Kecataman Kedungbanteng Kabupaten Banyumas,” Transient: Jurnal Ilmiah …, pp. 24–34, 2012.
R. A. Subekti, “Studi Kelayakan Pengembangan Pembangkit Listrik Tenaga Minihidro Di Desa Sukamaju Kabupaten Garut Jawa Barat,” Jurnal Teknik Hidraulik, vol. 6, no. 2, pp. 105–116, 2015.
Y. I. Arianto and Wahyono, “Sistem Pengoperasian Dan Sistem Perawatan Pt. Pjb Up Brantas Plta Sutami Malang,” EKSERGI Jurnal Teknik Energi, vol. 13, no. 3, pp. 74–77, 2017.
J. L. Hutabarat, “(2019). Studi Analisis Eksitasi dan Governor Untuk Mengatur Tegangan dan Frekuensi Keluaran Generator pada pltmh raisan. jakarta.,” Jurnal Matrix, vol. 6, no. August, p. 128, 2016.
N. B. Azizah, S. Indriati, R. Widuri, and I. Shaferi, “Analisis Repair Maintenance Policy Dan Preventive Maintenance Policy Untuk Meminimalkan Total Maintenance Cost Pada Mesin Pleating Pt Duta Nichirindo Pratama,” Jurnal Ekonomi, Bisnis, dan Akuntansi, vol. 22, no. 4, pp. 404–420, 2021, doi: 10.32424/jeba.v22i4.1765.
U. G. Mada, “Analisis Kondisi dan Gangguan Pada Baterai Alkali 110 VDC di PT. Indonesia Power UP Mrica Sub Unit PLTA Wonogiri FAISHAL ALIM MAS UD, Budi Bayu Murti,S.T.,M.T.,” no. 15, p. 2016, 2016.
U. G. Mada, “Tinjauan Baterai 110 VDC sebagai suplai tegangan DC pada pembangkit listrik di PLTA Wonogiri NUR FITRIAH, Ma’un Budiyanto, S.T., M.T.,” 2017.
L. Lonteng, “Analisa Kemampuan Sumber DC (Baterai dan Charge) dalam Memenuhi Kebutuhan Gardu Induk Teling,” Analisa Kemampuan Sumber DC (Baterai dan Charge) dalam Memenuhi Kebutuhan Gardu Induk Teling, no. Dc, pp. 1–8, 2022.
D. Fitria, “Pada Pt Indonesia Power Program Studi S1 Manajemen,” 2019.
I. Nurhadi, “Analisis Kelayakan Battery 110 VDC Dalam Mengsuplai Pembebanan ( Studi Kasus Gardu Induk Perawang 150 kV ),” IJEERE: Indonesian Journal of Electrical Engineering and Renewable Energy, vol. 2, no. 1, pp. 29–38, 2022, doi: 10.57152/ijeere.v2i1.179.
P.T PLN IP Sub Unit, “sejarah PLTM Gunung Wugul,” vol. 10, p. 6, 2021.
A. B. Djauhari, Perencanaan bendung pembangkit listrik tenaga minihidro di kali jompo skripsi. 2012.
M. A. Pahlevi, R. Junaidi, and F. Hc, “Prototipe baterai berbasis karbon aktif dari bambu betung (tinjauan pengaruh karbon aktif dan elektrolit dalam meningkatkan daya baterai),” Kinetika, vol. 11, no. 01, pp. 55–60, 2020.
A. 1, Borni Florus King, Seno Darmawan Panjaitan Hartoyo, “SISTEM KONTROL CHARGING DAN DISCHARGING SERTA MONITORING KESEHATAN BATERAI,” vol. 15, no. 1, pp. 165–175, 2016.
S. N. Lubis, “Kegagalan Proteksi Pada Gardu Induk 150 kV Akibat Suplai Tegangan DC,” Sinusoida, vol. 19, no. 2, 2017.
S. Meliala, M. Rijal, and T. Taufiq, “Studi Kapasitas Baterai 110 Volt Dc Unit I Pada Gardu Induk 150 Kv Bireuen,” Jurnal Energi Elektrik, vol. 10, no. 2, p. 1, 2021, doi: 10.29103/jee.v10i2.6202.
Yusuf Alfianto, “Pemeliharaan sistem DC Battery Di GTG PLTGU Blok 1 Tambak Lorok PT. Indonesia Power UP Semarang,” 2018.
Cahyo Adhi Nugroho, “Pemeliharaan tahunan sistem DC (Baterai 48 volt) di Gardu Induk 150 Kv Srondol.” 2018.
T. Djunaedi and C. Dimyati, “Pemeliharaan Sistem Suplai Ac/Dc,” p. 38, 2014.
anggita sari, “Sejarah Perusahaan Bab Ii,” Book, pp. 8–24, 2019.
E. Nurtiasih, P. E. Pambudi, and S. Priyambodo, “Analisa Kapasitas Baterai Komunikasi Pada Gardu Induk 150 kV Bantul,” Jurnal Elektrikal, vol. 4, no. 2, pp. 46–53, 2017.
Zito Tomas Dos Reis, “Analisis penurunan kapasitas baterai 110 volt unit I di GI 150 kv kentungan,” Jurnal Elektrikal, vol. 4, no. 1, pp. 10–20, 2017.
R. Agned, “205450-Studi-Kapasitas-Baterai-110-Vdc-Pada-Gar(1),” pp. 1–9, 2013.
Hawa, S. D., Syauqi, A., Rolisnawati, R., & Za'im Akbar, H. (2023). Factor Analysis of Demand for Kaligua Tourism in Brebes Regency: A Case Study Using Primary Data. Media Trend, 18(1), 90-101.
Al Banin, Q., Eliyana, A., & Latifiyah, E. R. (2020). Enhancing employee performance with work motivation as a mediation variable. Systematic Reviews in Pharmacy, 11(9), 333-346.